As reported on November 20, 2026, Ethereum’s Glamsterdam upgrade could be delayed until late January 2027 at the earliest. Core developers also discussed a possible delay until May 2027. Neither date was presented as a settled schedule.
More than 50 affected application teams may have until mid-January to patch their code. Smart-contract deployment gas costs are expected to rise sharply under the upgrade, and unpatched code could fail as a result. The Ethereum Foundation, ChainSecurity and Dedaub have contacted at least 50 affected companies; three projects were classified as high-impact.
Developers were still weighing whether to retain the existing specification or change it. The reported cost increase and compatibility risk therefore concern an upgrade whose specification and timing remained under discussion.